Create the project scope
Scope: List all the foreseeable main tasks/items that need to be delivered to complete the project. Tasks/items are planned into iterations, given priorities, and they contain an initial estimation of the amount of work involved. Tasks/items for iterations 1 and 2 should be presented in detail, including sub-tasks, priorities and times. Tasks/items for iterations 3 and 4 are expected to be presented in less detail. The tasks of the second iteration are defined at the proper level of granularity (90% of tasks take less than 16 hours, and no task is larger than 40 hours). Tasks should have descriptions, and the latter should be understandable.  [Scope example](https://moodle.ut.ee/pluginfile.php/2536753/mod_resource/content/3/Scope-wiki-example.pdf)